Minutes of CGM Open Telecon - 24 January 2003
Participants
Dave Cruikshank, Boeing
Kevin O'Kane,Auto-trol
Ulrich Laesche, Ematek
Don Larson, Larson Software Technology
Forrest Carpenter, SDI
Andrew Moorhouse, MOD UK
John Gebhardt, Corel
Gabriella, Rist,Individual (Lieberr)
Lofton Henderson, Program Director
Agenda/Discussion
Product web pages
General Approach
- Move WebCGM navigation in navigation pane up from the technical
page to the same level as technical on the main CGM Open home
page
- Replace "Resources" line in navigation pane with "WebCGM
& Products" and move Resources down to WebCGM home page
- Acition Item: Lofton will work with the OASIS web master to
accomplish this
Specific critiques
- Each of the main sub pages in the WebCGM home page should have
a link bar at top and bottom to go to WebCGM Home, Overview, FAQ,
and Products
- Overview page
Put a running heading (title line) for each paragraph and put
a TOC at the top of the page to link to each of them
Move the last paragraph (WebCGM supports the following "intelligent"
functions:) and bulleted list to the top of the page.
- Further readings page
Remove "further readings" page and change link for "further
readings" to point to the "suggested readings"
page. Move content of "further reading" to "suggested
readings" page
- Product pages
Under title for product type pages, add links to the other product
types (suggestion)
Plan for updates
- Short term
Dieter will update the pages as described above and below.
If typos are found communicate them directly to Dieter.
- Longer term
Gabriella will work on a more artistically pleasing design for
the pages, possibly to be implemented in the April time frame.
Schedule
- All updates are due to Dieter by Tuesday, Jan 28, 2003
- Go live as soon as possible (as Dieter's schedule allows)
- Vendor proformas are produced and implemented on April 1, 2003
- Web site is updated quarterly after that as needed
Vendor listings
Proformas
- A proforma is not necessary for Services and Miscellaneous
- Change links on product pages from "WebCGM Support"
to "Implementation Support Statement"
- Action Item
- Each vendor to ensure that the "implementation support
statement link links to the correct proforma and notify Dieter
if there is an error
- Blank proformas are hosted on the web site, once they are filled
in the vendor site will host it's own implementation support statement
in the form of the proforma
- At the beginning of each proforma in the Product area of each
proforma, in addition to product name, release/version, and platform,
we need to add latest proforma update date.
- Action Item:
- Dieter to make sure product area of each proforma is aligned
with the above requirement
- A determination was made to separate out core requirements from
extensions (symbol libraries, ESCAPES, and registered color models)
- The first part of the proforma table (all functional overview)
- Change to title for key 2 to "Supports all static core
functionality"
- Add a row for key 3 to say "Supports all extensions to
core functionality - for all modules below, satisfies requirements
- Change keys 2.11 and 2.12 to 3.1 and 3.2
- Unicode is another area that needs further dicussion.
- Action Item
- Dieter and Lofton will work on this proforma
- In the first paragraph of the introduction, chanage the wording
of the links to "interpreter implementation support statement"
and "generator implementation support statement"
The above links to link to blank proforma or completed proformas
after April 1 Add a preliminary section to the proforma table
dealing with preservation of primitives or elements Go forward
with the above addition
Action Item
- Kevin will update proforma a forward it to Dieter by Monday,
Jan 27,2003
- Toolkits
Long term goal to align these two proformas
- Interpreters
Add Hatch Style Definition
Go forward with the profile after above addition
Action Item:
Forrest will update this proforma and forward to Dieter
- Generators
Go forward with this proforma
- Transcoders
Go forward with this proforma
Product affirmations
- Don has submitted
- Ulrich will submit over weekend
- Kevin will update with an additional product
|